Walls:

How the 3D shape is generated into a buildable wall
Sometimes pictures are too small for their quality, feel free to open them in a new tab


render
Fig. 1: Impression of how the outside walls look like

This chapter will focus on how each wall is being built. First the focus is on how all the walls will look like. Then it will explain the bricklaying patterns and the process of building it.


Flowchart

In the 0_Introduction chapter the whole process of the design was shown. There were 5 groups that were dealt with individually. The walls are relatively simple. The process behind the walls is showed in this flowchart.

flowchart
Fig. 2: Flowchart of the walls

Then for all the elements bricklaying needs to be developed, both in detail as in construction methods. The choice is made with several considerations. These are shown in the following flowchart.

flowchart
Fig. 3: Bricklaying considerations


Develop the walls

From the 2_Forming chapter in Rule N11 the wall thickness and height is added. From the configuration hexagons work well with making quite easy builds. The main idea of the design is that the hexagons are extruded vertically and then domes are built on top of them. This is realisable as hexagons are easier with this than rectangles are. The walls are therefore in shape quite easy. There are four different kinds of domes, so there are also four types of wall-thicknesses. In the structural report the following diagram was shown:

diagram
Fig. 4: Diagram for wall thicknesses

In this picture it shows that there are 4 different kind of wall thicknesses, depending on the dome size. These thicknesses are 0.5m, 0,8m, 1.0m and 1.2m. The whole Hammam is made with these sizes, to make it a bit doable and understandable on how to do bricklaying in the project.

walls
Fig. 5: The walls without extrusion


Bricklaying

The flowchart in Figure 3 shows the considerations between rectancular bricks and triangular bricks. The first input is the brick size.

Considering the optimal brick form and dimension it was decided to start with a rectangular brick of 40 x 20 x 10 cm since this brick proportion is beneficial to form steps and lies under the maximum weight limit that a mason can handle.

The necessary wall thickness was based on the rule of thumb that an adobe wall of a dome should be one sixth of the dome diameter. Since the domes were designed with 2.4, 4.8, 7.2 and 9.6m diameter, the thicknesses was assumed to be at least 0.6, 0.8, 1.0 and 1.2m. The wall thickness of 0.4m was omitted due to practical reasons, this thickness does not offer sufficient surface area to place vaults on top.

Subsequently standard brick patterns as they have been used for centuries e.g. the half, cross and Flemish bond were tested for the number of necessary off-cuts. The design of the hammam is featured through hexagons so it was checked how the various wall thickness and bonds perform on the many sixty degree corners. As expected the result was that the rectangular brick bonds required a various number of off-cuts. However the number of off-cuts required was disappointing. In addition the same procedure was performed with rammed earth wall constructions but the result was again a high level off cuts. Even the application of tailor-made bricks was not satisfying. An even a higher number off-cuts was expected for the 120 degree corners for the archways.

walls
Fig. 6: In white the off-cuts are shown, per layer this already results in 24 off-cut bricks

walls
Fig. 7: In white the off-cuts are shown, per layer around 18 off-cut bricks

The higher the number of off-cut bricks the less effective is the wall construction.


Considering the triangular grid of the project the idea was obvious to run the same procedure with equivalent triangular bricks. When staggering the bricks above each other and rotating them alternately by 60 degrees a bond was achieved. By doing so the wall edges were graded. Here another trapezoidal brick had to be introduced so that smooth walls can be achieved. The triangular brick in combination with the small trapezoidal brick required no off-cuts to produce the 60 degree corners, independent from the wall thickness. For compatibility the triangular wall dimensions were modelled close to the rectangular brick, with side lines of 40cm and a height of 10cm. This resulted in the following bricklaying patterns:

walls
Fig. 8: Using triangular bricks will result in having no cutt-off bricks

There is one following of this, that is the bricksize is following the triangular grid. As the grid used, consists 0.4 meters, the height of the brick is an irrational number, as it is the sqrt of 0.12. With the trapezoid in this, there will always be wall thicknesses with the sizes:
(n + 1/3) * sqrt(0,12), where n is the amount of bricks in the width. But this is not a problem, as the new thicknesses are actually quite useful. It will result in thicknesses of (rounded) 0.5m , 0.8m and 1,2meters. For the smallest walls it is not a problem if they are scaled down to 0.5 meters thickness and for the 1meter wall something else will need to be thought of. This is done by using infill, a bit like the roman style. Rammed earth isn't prefered, since it might not settle and foamwork is required. By using rectangular bricks in the infill, the perfect width is reached.

walls
Fig. 9: Also fill-in can be used

The result for the 120 degree corners of the archways were equally positive. It was advised to dull the sharp corners to reduce injuries and prevent the edge to break off. The triangular brick bond allows to dull the edge easily with only every second brick to be slightly amended i.e. cutting off a small protruding edge.

walls
Fig. 10: Corners

For the walls, the decision was made to stick with the triangular bricks, for quite obvious reasons. The only thing that could change this decision is if there are hard problems with doors. In the hexagons there are 6 smaller elements that combined form the hexagon.

When combining all the triangles it is important that it can also be mirrored, as the bricks should switch every layer. By using these 6 elements, each layer can be mirrored and thus a sturdy wall can be realised.

walls
Fig. 11: Each element will look like this

walls
Fig. 12: And combined they are mirrored

For this project a script was developed that included all of our approach. Go to scripts


Construction

So to construct the wall, first the foundation has to be built. The first step is setting out the hexagon on the site. In this example, a hexagon with a diameter of 9.6 meter is used.

walls
Fig. 13: Setting out the hexagon on site

To set out the hexagon, residents of the camp can easily do it without very hard tools. The following steps should be taken:

walls
Fig. 14: Setting out the hexagon on site

1) Determining the center of the hexagon and pound in a steel post.
Tying a rope to the base of the post. Tying a steel pole to the other end of the rope. The length of the out-stretched rope will be the radius of the circle for the hexagon.

2)By stretching the rope, drawing a circle with a steel pole attached to the other end of the rope, just like making a circle with a compass.

3)Setting a post on the circular line to determine the first corner of the hexagon.

4)Using the same length of the radius to determine the next corner point of the hexagon.

5)Working from one point to the next using the same length of the radius.

6)The precision can be checked by working from the same starting point but in the other direction.

7)A perfect hexagon is established. It is advisable to cover the tops of the steel rods with a ball or a plastic bottle in order to make them visible and to prevent injuries.

Then, measure another 70 centimeters around the hexagon. More space is needed to make sure the foundation is accessible and later on functions as a chimney and is needed for the excess of moisture. Then dig out the needed ground.

walls
Fig. 15: Measure an extra 70 centimeters

walls
Fig. 16: Dig out 1 meter deep.

Now make the foundation with rocks. Make sure this goes a little wider on the bottom, as shown in figure 18. Normal rocks are sufficient to build this foundation.

walls
Fig. 17: Make the foundation.

walls
Fig. 18: Section of the foundation.

Now start building the wall. This is the wall until ground level, that follows the bricklaying that has been discussed before. Build vaults in the inner place, they are needed for floor heating, but also for moist. These are build like normal vaults, more on that is found in the corridor chapter. Lastly fill everything up with earth, so that a smooth floor is the result.

walls
Fig. 19: Make walls until the needed height

walls
Fig. 20: Make vaults that are needed for heat. This is basicly the floor heating.

walls
Fig. 21: Fill with earth